Paid Through 6/30/2024
4//2023 | Margali & Flynn | Retainer (50% of fee) | $7500 |
11/29/2023 | Eli Cabinetry | Deposit for custom Cabiner | $3900 |
11/29/2023 | MPS Electric | Deposit | $2270 |
11/29/2023 | Margali & Flnn | Furniture,carpet,shades,tile,wallpaer,installation, etc | $48,897.89 |
11/29/2023 | Matelsky | Depost | $10,000 |
2/9/2024 | Matelksy | Due after Demo and carting | $50,000 |
3/11/2024 | Luigi Gileno Architect | Retainer | $5,250 |
4/11/2024 | Village N Hills | Permits | $1,050 |
5/1/2024 | Matelkiy | Bathrooms, office, storage, floor, stairs, headers, etc | $50,000 |
5/8/2024 | Matelsky | Flooring, Basement hall, raililngs, vestibule doors | $50,000 |
5/29/2024 | Matelsky | Sheetrock | $62,225 |
6/14/2024 | Matelsk | Office: closet, alcove, doors, shelves, molding, AV PREP TV | $54,525 |
TOTAL $345,617.89
Margali & Flynn | Retainer bal. + added design fees + furniture carpet bal | $20,000 |
Legacy Transport | Freight and warehousing | $ 3,000 |
Abbale Plumbing | Bath fixtures Toilet, handles faucetsm sinks, etc | $6430 |
Gramman Plumbing | Demo & prep 2 bathrooms, relocate fixtures for ADA | $16,765 |
Luigi Gelino Architect | Balance due | $13,000 |
Matelsky / MPS Elec | Baths, office , closet, lighting, keypad, GC fee, etc (20%) | $40,009 |
Matelsky | On completion | $2,600 |
Village of n hills | Inspection fees, etc | $2,000 |
Artwork | to be selected | $10,000 |
Eli Cabinetry | balance due | $3,900 |
TO BE PAID | $117,704 | |
Total to be paid | $463,321.89 |